ⅠBackground
Taiwan’s exports expanded rapidly in the 1960s, but infrastructure such as ports, railways, highways, and electricity gradually fell behind demand. Ships were congested at Kaohsiung and Keelung harbors; the Western Trunk Line, limited to steam and diesel locomotives, was crowded and often delayed; passenger and cargo volume at Songshan Airport was approaching capacity; and steel and petrochemical raw materials were largely imported. Historical materials from the Directorate-General of Budget, Accounting and Statistics note that Yen Chia-kan had already recognized the problem of insufficient public investment while serving as Premier, and planning for several of the projects had long been under way.
In the early 1970s Taiwan faced a series of shocks: it withdrew from the United Nations in 1971, and in October 1973 the first oil crisis broke out, bringing rising oil prices, shortages of goods, and global stagflation. Chiang Ching-kuo, who became Premier in 1972, decided to respond to the recession and promote industrial upgrading through large-scale public investment, leaving behind his famous remark: “If we don’t do it today, we will regret it tomorrow.”
ⅡWhat Happened
On November 12, 1973, in his administrative report to the Fourth Plenary Session of the Kuomintang’s Tenth Central Committee, Chiang Ching-kuo announced nine major national construction projects to be completed within five years. The Executive Yuan Council formally adopted the plan on November 22, and the nuclear power plant already under construction was later added, making them collectively the “Ten Major Construction Projects.” Six were transportation projects: the North–South Freeway (Sun Yat-sen Freeway), railway electrification, the North-Link Railway, Chiang Kai-shek International Airport (today’s Taoyuan International Airport), Taichung Harbor, and Su’ao Harbor. Three were heavy and chemical industry projects: an integrated steel mill (China Steel Corporation), a large shipyard (China Shipbuilding Corporation), and the petrochemical industry. One was an energy project: the First Nuclear Power Plant.
The projects were completed one after another during the 1970s. Construction on the Sun Yat-sen Freeway began in August 1971, and the entire 373-kilometer route opened in October 1978, with a total budget of about NT$42.9 billion. The first phase of Taichung Harbor began in November 1973 and was completed in October 1976. The two units of the First Nuclear Power Plant were completed in 1977 and 1978. The electrification of the Western Trunk Line was celebrated with an opening ceremony at Kaohsiung Station in July 1979. Because of its difficult tunnel works, the North-Link Railway did not open along its full length until February 1, 1980. Many of the projects were built under contract by the Retired Servicemen Engineering Agency.
The funding required was enormous. According to estimates made when the central government budget for fiscal year 1975 was drawn up, the ten projects would require about NT$190.4 billion from fiscal years 1975 to 1979, roughly 2.5 times the central government’s total final expenditures that year. The government raised funds through multiple channels, including the budget, government bonds, foreign loans, and self-financing by state-owned enterprises, and Minister of Finance K. T. Li also sought loans from countries such as Saudi Arabia.
ⅢImpact
The Ten Major Construction Projects are widely credited with helping Taiwan weather the recession that followed the oil crisis. According to a 1979 assessment by the Council for Economic Planning and Development, Taiwan’s economic growth rate rebounded from 0.6% in 1974 to 11.5% in 1976, with the Ten Major Construction Projects contributing about 2.6 percentage points; the projects directly created about 146,000 jobs. The Sun Yat-sen Freeway roughly doubled road transport capacity on Taiwan’s main island. When the North-Link Railway opened, it connected the eastern railways to the western trunk lines for the first time; originally expected to lose money, it later became a popular route.
In the long run, the steel, shipbuilding, and petrochemical industries increased self-sufficiency in raw materials and spurred the development of midstream and downstream industries, while the freeway and harbors improved the investment environment and accelerated the development of industrial zones near interchanges. From 1973 onward, heavy industry’s share of manufacturing exceeded that of light industry for the first time, and the economic structure shifted toward heavy and chemical industries. After the Ten Major Construction Projects, the government launched further programs such as the Twelve Construction Projects and the Fourteen Construction Projects, but their impact is generally considered not comparable to that of the original ten.
ⅣControversies & Perspectives
The Ten Major Construction Projects faced considerable skepticism even at the time. With so many massive projects launched at once, amid the oil crisis and diplomatic difficulties, public opinion criticized the risks as too high, and the Sun Yat-sen Freeway was criticized as being built for the few wealthy people who owned cars. According to the Oral History of Mr. K. T. Li, Li, then Minister of Finance, did not know about the announcement in advance. Although he afterward did his utmost to raise funds, he once described such projects as “grandiose” and “extravagant,” and later said their success had been achieved “by happy accident.”
Economist Kao Charng argues that the Ten Major Construction Projects eased economic stagnation but also had the side effect of high inflation: Taiwan’s inflation rate reached about 47.5% in 1974 (Directorate-General of Budget, Accounting and Statistics data, as cited in the Chinese Wikipedia article on the Ten Major Construction Projects), though this was also linked to the surge in international oil prices. Others point out that most of the ten projects consolidated and accelerated existing plans, some even building on foundations or blueprints from the Japanese colonial period, and that they bore a strong stamp of the planned economy. The narrative crediting a single leader is also seen as overlooking the long-term preparation of the economic and financial bureaucracy.